Assam-Meghalaya villagers oppose Kulsi hydropower project
- Who
- Villagers of Bodo, Garo, Khasi and Rabha communities, Meghalaya's traditional chiefs, and the Assam and Meghalaya governments.
- What
- Local people are protesting a joint 55-MW hydropower-cum-irrigation project planned on the Kulsi river.
- Where
- Near Ukiam on the Assam-Meghalaya border, about 80 km southwest of Guwahati.
- When
- The project was announced in June 2025; the protest is reported in October 2026.
Why it matters
The Kulsi project brings together three tensions: energy and irrigation needs, the survival of an endangered species, and the rights of tribal communities over their land. More than 2,000 people have protested.
Three traditional chiefs in Meghalaya have refused consent, pointing to the need for No-Objection Certificates (NOCs) for land-related development.
What it means
The 62-metre dam is expected to affect 46 villages across both states, so displacement and loss of livelihoods are the main local concerns. The river is also a habitat of the Gangetic dolphin, and dams fragment such habitats and alter river flows.
The project aims to produce 55 MW, irrigate about 26,000 hectares and help control floods. Without the chiefs' consent, work on land they control is likely to stall.
What it changes
Nothing concrete has changed yet; the project is still at the planning stage. What has changed is the organised opposition, led by the Assam-Meghalaya Joint Protection Committee (AMJPC), formed in 2025.
Community consent is now the key hurdle, because in Meghalaya chiefs hold significant authority over land, especially in Sixth Schedule areas. The site's closeness to disputed border sectors such as Borduar and Langpih adds a further complication.
Historical context
The Assam-Meghalaya border dispute dates from 1972, when Meghalaya was carved out of Assam as a separate state. It involves 12 disputed sectors along an 884-km border.
The Sixth Schedule, under Articles 244(2) and 275(1), provides for the administration of tribal areas in Assam, Meghalaya, Tripura and Mizoram through Autonomous District Councils. It reflects the constitutional commitment to protect tribal land and custom.
Why this is relevant for UPSC
This touches GS3 (Environment: conservation, impact of infrastructure projects on biodiversity; Infrastructure: energy and irrigation), GS2 (Federalism: inter-state disputes; Sixth Schedule) and GS1 (tribal society).
It serves both papers. Prelims can ask about the dolphin's status and the Sixth Schedule, while Mains can use it as a development-versus-environment case.
Important facts for Prelims
- The Kulsi project is a joint 55-megawatt hydropower-cum-irrigation scheme of Assam and Meghalaya.
- It is planned to irrigate about 26,000 hectares and mitigate floods.
- The dam would be 62 metres high and affect 46 villages.
- The Kulsi is formed by the confluence of the Dron, Shree and Dilma rivers.
- The Gangetic dolphin is India's National Aquatic Animal.
- It is listed as endangered by the International Union for Conservation of Nature (IUCN).
- It is protected under Schedule I of the Wildlife Protection Act, 1972.
- The Assam-Meghalaya Joint Protection Committee (AMJPC) was formed in 2025.
- The Sixth Schedule rests on Article 244(2) and Article 275(1).
- The Assam-Meghalaya border is 884 km long, with 12 disputed sectors.
Themes for Mains
- Development versus conservation: Hydropower and irrigation bring benefits, but dams threaten river dolphins and fragment habitats. A way forward is a rigorous environmental impact assessment, mitigation measures and exploring alternatives.
- Tribal consent and land rights: The refusal of chiefs raises the question of free, prior and informed consent. Strengthening Autonomous District Councils and transparent consultation can reduce conflict.
- Inter-state cooperation: A joint project near disputed sectors tests cooperative federalism. Settling the border dispute and shared benefit arrangements would help.
This is our own brief, written for UPSC preparation. It is not the text of any article.